With temporary heat in place, construction continues to move forward inside the Sanford Health Athletic Complex. Much of the underground work has been done in anticipation of new concrete floors being poured on ground level, and the old swimming pool is nearly filled in.
New walls are being built on second floor under the balcony seating area and around the wrestling practice room, and installation of new mechanical equipment continues on third floor.
Outside the building, crews continue to build roofs over the west and north expansions in an effort to enclose the new construction, and trusses arrived for the Nodak Mutual Insurance basketball training facility.
Check out the photo gallery and video above, and stay tuned to GoBison.com for monthly updates from the construction site.
With temporary heat in place, construction continues to move forward inside the Sanford Health Athletic Complex. Much of the underground work has been done in anticipation of new concrete floors being poured on ground level, and the old swimming pool is nearly filled in.
New walls are being built on second floor under the balcony seating area and around the wrestling practice room, and installation of new mechanical equipment continues on third floor.
Outside the building, crews continue to build roofs over the west and north expansions in an effort to enclose the new construction, and trusses arrived for the Nodak Mutual Insurance basketball training facility.