Sanford Health Athletic Complex Construction Update: August 2015
8/18/2015 9:00:00 AM | General, Facilities
AUGUST 2015 PHOTO GALLERY
With fall quickly approaching, the next milestone inside the Sanford Health Athletic Complex is enclosing the Scheels Center.
New insulation and paneling is being installed on the west side, and glass is being installed on the second floor of the south addition.
Outside, the west half of the south parking lot will be completed in the next week so work can begin on the east half of the lot near University Drive.
Check out the photo gallery and video above, and stay tuned to GoBison.com for monthly updates from the construction site.
With fall quickly approaching, the next milestone inside the Sanford Health Athletic Complex is enclosing the Scheels Center.
New insulation and paneling is being installed on the west side, and glass is being installed on the second floor of the south addition.
Outside, the west half of the south parking lot will be completed in the next week so work can begin on the east half of the lot near University Drive.
Check out the photo gallery and video above, and stay tuned to GoBison.com for monthly updates from the construction site.